August 4, 2026 — Dominion Energy’s Coastal Virginia Offshore Wind project is 81% complete and anticipated for completion at the end of 2027 – six months beyond the company’s earlier time frame and at least $228 million over cost estimate, thanks to tariffs and network upgrade costs assigned by PJM Interconnection grid operations.
Blue cited weather, moving equipment onsite and longer installation times for the planned 176 Siemens Gamesa 14 MW turbines among factors in the revised schedule.