February 2, 2026 — Within days of resuming work at Dominion Energy’s Coastal Virginia Offshore Wind project and Avangrid’s Vineyard Wind 1, both projects have marked key milestones. The projects argued they were at critical stages of construction in court and received preliminary injunctions to prevent the Trump administration from enforcing a stop-work order.
Dominion Energy provided a detailed update on the status of its project, reporting it has reached 71 percent completion and, critically, the first wind turbine generation was installed in January. The company’s massive wind turbine installation vessel, Charybdis (the only U.S.-flagged WTIV vessel), also began loading in December after a lengthy commissioning process and is deployed for the installations.
The presentation outlines that the project remains on track to generate its first power this quarter. Although after the delays due to the stop-work order from the Bureau of Ocean Energy Management, they have rescheduled completion to early 2027.