US district judge lifts stop-work order on Ørsted offshore wind project

Sptember 23, 2025 — A U.S. judge has lifted a stop-work order on Ørsted’s Revolution Wind project, a large offshore wind installation off the nation’s East Coast.

The Revolution Wind project, which is being built off the coast of the U.S. state of Rhode Island, was halted in August after the Bureau of Energy Ocean Management (BOEM) issued a stop-work order, just weeks after it also canceled all offshore Wind Energy Area designations. BOEM issued a director’s order to halt “all ongoing activities” related to the project, which Ørsted said was 80 percent to completion.

Read the full article at SeafoodSource

Judge rules against Trump administration, allows Revolution Wind to resume

September 23, 2025 — A federal judge on Monday ordered that Orsted’s Revolution Wind may resume construction, affirming the company’s arguments that the Trump administration’s halting of the project is unlawful.

The ruling is a major win for the offshore wind industry, which to date has not seen much relief from the courts in addressing the obstacles that the Trump administration has put in place through executive and secretarial orders.

The preliminary injunction, as the name suggests, is a preliminary decision that halts the stop-work order while the case plays out. Still, such an injunction must meet four conditions, including that the plaintiff (Orsted) is likely to succeed on the merits of their argument and suffer irreparable harm without relief, and that an injunction would be in the public interest.

Read the full article at The New Bedford Light

Judge Says Work on Wind Farm Off Rhode Island Can Proceed, for Now

September 22, 2025 — A federal judge ruled on Monday that the Danish energy company Orsted could restart work on Revolution Wind, a large wind farm off the coast of Rhode Island that is nearly complete but had been abruptly halted last month by the Trump administration.

Judge Royce Lamberth of the U.S. District Court for the District of Columbia granted a preliminary injunction in a lawsuit that the developers of Revolution Wind had filed challenging the Interior Department’s stop-work order. The injunction means that construction can continue while the case moves forward.

“Revolution Wind will resume impacted construction work as soon as possible, with safety as the top priority,” Orsted, which is developing the wind farm in a joint venture with Skyborn Renewables, said in a statement. Orsted added that it would “continue to seek to work collaboratively with the U.S. administration and other stakeholders toward a prompt resolution” of the lawsuit.

The $6.2 billion Revolution Wind project was 80 percent completed when the Interior Department ordered construction to stop on Aug. 29. The developers behind the 65-turbine project had said it was on track to generate enough electricity for more than 350,000 homes in Rhode Island and Connecticut by next spring.

Read the full article at The New York Times

The Feds Had Questions. Court Filings Claim Revolution Wind Developers Didn’t Answer Them

September 17, 2025 — President Donald Trump’s opposition to offshore wind crystallized long before he won re-election. But the justification for the administration’s abrupt halt to the Revolution Wind project on Aug. 22 has remained murky.

Until now.

New court filings from the U.S. Department of Justice reveal the rationale behind the U.S. Department of Interior’s (DOI) decision to shut down the 65-turbine project that was already 80% finished: Developers allegedly failed to turn in required plans on how the project off Rhode Island’s coastline would affect national ocean research and defense work.

“As of the date of this Declaration, still DOI not received any information that these requirements have been satisfied and given how long they remain pending, the department has concerns as to whether they will ever be met,” Adam Suess, acting assistant secretary for land and minerals management for the Interior Department, wrote in a Sept. 12 affidavit.

Suess’ written testimony counters the criticism from state officials and project developers accusing the Trump administration of arbitrary and unlawful abuses of power in a pair of federal lawsuits filed Sept. 4.

Ørsted and Skyborn Renewables, co-developers of the $5 billion wind project, filed their lawsuit against Interior Secretary Doug Burgum and other federal agencies and directors in D.C., while attorneys general in Rhode Island and Connecticut took their legal challenge to Rhode Island federal court. The two southern New England states were under contracts to buy electricity from the 704-megawatt project starting next year. Now in limbo, thousands of labor jobs are on the line, along with both states’ abilities to meet their climate change mandates and the reliability of the regional electric grid.

Read the full article at Rhode Island PBS

Orsted Sues Over Stop-Work Order

September 12, 2025 — Revolution Wind, a wind farm under construction in federal waters on the outer continental shelf, has sued the Trump administration following the federal Bureau of Ocean Energy Management’s August issuance of a stop-work order, with the 65-turbine installation already 80-percent complete.

The stop-work order was one of multiple actions apparently aimed at killing a nascent domestic offshore wind industry. In July, the federal Interior Department announced the end of what it called “preferential treatment for unreliable, subsidy-dependent wind and solar energy,” and in August launched investigations into bird deaths caused by wind farms. BOEM rescinded regulations outlining renewable energy lease sales early last month.

Read the full article at The East Hampton Star

Could Revolution Wind get back to work? Burgum comments suggest anything is possible.

September 11, 2025 — A week after Gov. Dan McKee asked to meet with President Donald Trump over the administration’s halt to the Revolution Wind project, he’s still waiting for an answer.

But U.S. Interior Secretary Doug Burgum is suggesting the paused project might not be dead in the water after all. In an interview on CNBC Wednesday, Burgum, whose office oversees federal permits for offshore wind projects, indicated the administration was open to letting work resume on the 65-turbine project.

Read the full article at Yahoo News!

Ørsted and Iberdrola Are Trying to Save U.S. Offshore Wind Investments

September 9, 2025 — Two major offshore wind developers,  Ørsted and Iberdrola, have efforts underway to save their offshore wind projects in the United States. The companies are reportedly trying to win over the Trump administration, which opposes offshore wind energy, by emphasizing the larger investments in the United States.

Energy Secretary Chris Wright, Bloomberg reports, confirmed that the administration is “actively engaged in discussions” with Ørsted over the future of the Revolution Wind project off the coast of Rhode Island and Connecticut. According to the reports, Wright, during a presentation at the Council of Foreign Relations, confirmed that there is “a very active dialogue,” saying the issues of the wind farm were being “worked and discussed.”

Last month, the Trump administration issued a stop work order for the project, which Ørsted said is 80 percent installed. The company highlighted its large investment, saying that all of the foundations for the 704 MW wind farm are installed and that 45 out of the 65 wind turbines have also been installed. The export cabling and the onshore power substation are nearly complete.

Ørsted filed a lawsuit challenging the legal authority to suspend the project, calling it a necessary step. The company, however, also said it was continuing to seek a resolution with the administration.

Read the full article at The Maritime Executive

How many lawsuits does it take to restart Revolution Wind? More than one.

September 8, 2025 — Hours before a federal judge in Boston was set to hear arguments on the Trump administration’s executive order stopping offshore wind reviews, two separate lawsuits seeking to reverse the recent stop work order on nearly completed Revolution Wind project were announced Thursday.

Revolution Wind, a joint venture between Ørsted and a consortium led by Skyborn Renewables, filed a lawsuit in the U.S. District Court in Washington, D.C. challenging the stop work order issued Aug. 22 by the U.S. Department of Interior’s Bureau of Ocean Energy Management (BOEM). The multibillion dollar project was 80% complete and scheduled to begin delivering 704 megawatts of power to 350,000 homes across Rhode Island and Connecticut starting in mid-2026.

Meaghan Wims, an Ørsted spokeswoman, said the company will continue to seek to work collaboratively with the Trump administration and other stakeholders but believed the federal government lacked legal authority for the stop work order. All required federal and state permits for the 65-turbine wind farm in Rhode Island Sound were secured in 2023 after a review process that lasted seven years.

“The project is facing substantial harm from continuation of the stop-work order, and as a result, litigation is a necessary step,” Wims said.

Soon after Ørsted and Skyborn Renewables filed their lawsuit, Rhode Island Attorney General Peter Neronha informed reporters of his intention to file a lawsuit with his Connecticut counterpart seeking to reverse the Trump administration’s decision. The lawsuit was filed Thursday afternoon in the U.S. District of Rhode Island in Providence.

“We have begun and built an industry here in Rhode Island that can continue to grow and provide jobs to Rhode Islanders and build our economy,” Attorney General Peter Neronha told reporters at a morning press conference in his Providence office. “We’re on the cusp of building that economy, and the president stopped it unlawfully.”

Read the full article at Rhode Island Current

States and developer sue the Trump administration for halting work on New England offshore wind farm

September 5, 2025 — Connecticut, Rhode Island and the developer of an offshore wind farm that would power 350,000 homes in the two states said Thursday that they’re suing the Trump administration for stopping the nearly completed project.

Rhode Island Attorney General Peter Neronha accused President Donald Trump of waging an “all-out assault” on the wind energy industry. The states’ lawsuit, filed in U.S. District Court in Rhode Island, describes the Revolution Wind project as a “cornerstone” of their clean energy future, abruptly halted by federal officials without “statutory authority, regulatory justification or factual basis.”

Danish energy company Orsted filed a separate suit in U.S. District Court in Washington, D.C., also arguing that the administration lacks the legal authority to block the Revolution Wind project. Orsted said it would seek a preliminary injunction that would allow it to move forward with the project, which is 80% complete, with all underwater foundations and 45 of 65 turbines installed.

Read the full article at the Associated Press

Orsted’s Revolution Wind sues Trump administration over project halt

September 5, 2025 — Danish offshore wind developer Orsted (ORSTED.CO), and the states of Rhode Island and Connecticut sued the Trump administration on Thursday, alleging its decision to block construction of the nearly finished Revolution Wind project is illegal.

The separate complaints are the latest twist in a saga that started last month when U.S. officials issued a stop-work order to Revolution Wind, citing unspecified national security concerns. The order forced the suspension of a project that was 80% complete with all offshore foundations in place and 45 out of 65 wind turbines installed.

“The stop-work order was issued without statutory authority, lacks any evidentiary basis, and is unlawful,” Revolution Wind said in its complaint against U.S. Interior Secretary Doug Burgum and five other federal defendants. The suit was filed in U.S. District Court for the District of Columbia.

U.S. President Donald Trump has repeatedly criticized wind energy as ugly, unreliable, and expensive, and his administration is leaning on multiple federal agencies to rein in wind development.

Critics say Trump’s stance on offshore wind is at odds with his goal to boost energy supplies to power the nation’s ambitions around artificial intelligence, which requires a huge amount of data processing.

Read the full article at Reuters

  • « Previous Page
  • 1
  • 2
  • 3
  • 4
  • 5
  • Next Page »

Recent Headlines

  • MAINE: How fisheries in Maine are restructuring amid warming waters
  • A rare whale is having an encouraging season for births. Scientists warn it might still go extinct.
  • Could moon snails, neon flying squid fisheries save the scallop industry? Some local scientists are hopeful
  • Researchers Say the Oceans Have Passed a Milestone for Acidification
  • WASHINGTON: Crabbers catch fair winds, decent price
  • LOUISIANA: Louisiana’s Fisheries Are Complex. Let’s Base Decisions on Science, Not Assumptions.
  • US Congress rejects Trump’s NOAA Fisheries cuts in compromise budget proposal
  • Environmental organization sues federal government to protect horseshoe crabs in Maine and U.S.

Most Popular Topics

Alaska Aquaculture ASMFC Atlantic States Marine Fisheries Commission BOEM California China Climate change Coronavirus COVID-19 Donald Trump groundfish Gulf of Maine Gulf of Mexico Illegal fishing IUU fishing Lobster Maine Massachusetts Mid-Atlantic National Marine Fisheries Service National Oceanic and Atmospheric Administration NEFMC New Bedford New England New England Fishery Management Council New Jersey New York NMFS NOAA NOAA Fisheries North Atlantic right whales North Carolina North Pacific offshore energy Offshore wind Pacific right whales Salmon South Atlantic Virginia Western Pacific Whales wind energy Wind Farms

Daily Updates & Alerts

Enter your email address to receive daily updates and alerts:
  • This field is for validation purposes and should be left unchanged.
Tweets by @savingseafood

Copyright © 2026 Saving Seafood · WordPress Web Design by Jessee Productions