January 29, 2026 — After two other projects secured relief in the courts, Vineyard Wind on Tuesday also won a decision allowing it to resume “full activities” at its offshore wind power project south of Nantucket.
U.S. District Court Judge Brian Murphy in Massachusetts stayed the Bureau of Ocean Energy Management’s Dec. 22 project suspension order, which Vineyard Wind challenged on Jan. 15.
“As the legal process proceeds, Vineyard Wind will continue to work with the Administration to understand the matters raised in the Order,” Vineyard Wind said in a statement. “Vineyard Wind will focus on working in coordination with its contractors, the federal government, and other relevant stakeholders and authorities to safely restart activities, as it continues to deliver a critical source of new power to the New England region.”